Improvements to Parking Lot #2 Expected to Begin in Mid-October

Post Date:09/27/2019 2:40 PM

Parking Lot #2 in downtown Sausalito, located between Bay Street and the Bank of America building, will soon be getting a makeover. Work on the improvement project is expected to begin in mid-October and be completed by the end of the year.

The project includes improving drainage, regrading and resurfacing, and installing electrical infrastructure to support the possible future installation of a vehicle charging station. Subsurface repairs may be necessary to remove deteriorating wooden pilings below the parking lot.

A total of $385,000 was allocated for the project by the City Council at its meeting on September 24. The funding includes $356,536 for the base project and $28,464 to cover any unforeseen conditions. The work will be performed by CF Contracting, the lowest qualified bidder in a competitive bidding process that closed on September 13.

Any questions about improvements to Parking Lot #2 may be directed to Senior Civil Engineer Andrew Davidson at adavidson@sausalito.gov or (415) 289-4180.