Construction on Spencer Avenue

Post Date:01/31/2025 3:20 PM
Sausalito's Public Works Department will soon begin a project to upgrade the storm drainage system on Spencer Avenue between Sweet Briar Lane and San Carlos Avenue. Work is expected to get underway on February 3 and should be completed within two weeks.

The project will add additional capacity to a drainage system that has, at times, been overtaxed by heavy rain. Currently, the street relies on a single drainage inlet located at the lower end of Spencer Avenue.

Any questions about the upgrade project can be directed to Assistant Engineer Shehriyar Bukhari at (415) 289-4196 or sbukhari@sausalito.gov.

VIEW A MAP SHOWING THE CONSTRUCTION AREA ON SPENCER AVENUE