Design Questions

As proposed, Site 75 has 8 studios, 11 one-bedroom and 11 two-bedroom apartments. Site 84 has 47 one-bedroom and 3 two-bedroom apartments, including one proposed manager unit. Neither site currently includes three-bedroom apartments. These are proposed plans, not final construction drawings.
Our current concept leaves the existing slope by the tennis courts largely intact. There may be some localized retaining-wall work, but we cannot responsibly give a wall height, tree impact or cost until we have a survey and engineering. We propose this work publicly before asking anyone to accept the design.
Assume this is in reference to Site 84 (MLK site). No, our plan is not simply to dump two feet of dirt on the site. We need to establish the applicable flood and sea-level-rise elevations, drainage conditions and accessible routes before choosing a final solution. Raising some finished floors may be part of it, but it is too early to promise the exact approach.  Insurance also plays a role in setting the final elevation for residential units.  In past experience, first floor units could be raised with stoops. Major Bldg entries would remain at grade. There are elevators in each bldg to provide an accessible path of travel to the front door of each unit.
There are no three-bedroom apartments proposed at Site 84. The current plan is 47 one-bedroom and 3 two-bedroom apartments; one of the two-bedrooms is proposed for an on-site manager.
We have not proposed a path into Willow Grove. Before considering one, we would want to hear from neighbors and understand the ecological and maintenance impacts.
We have heard the concern about the north property line. We will inspect the existing wall and determine whether repair or replacement is needed. We also intend to work with the neighbors on a privacy fence, but the final material, height and design need review.

Infrastructure

We have included a preliminary allowance for typical site and off-site work, not a fully engineered Coloma drainage solution. We need a drainage study before we can say what improvements are necessary or whether the allowance is enough. If the scope is larger, we will show that cost rather than pretend it is covered.  Additionally, we would make sure both off-site and on-site drainage improvements follow stormwater best management practices (BMPs) for both sites.
Yes, and we agree this deserves a real engineering answer. Our civil engineer will study runoff, existing capacity and required stormwater controls. The final design must meet applicable standards including but perhaps not limited to the City of Sausitio and the SF Bay Area Regional Water Quality Control Board; we are not claiming that work is complete.
We do not yet know whether the existing sewer has enough capacity for this project and other planned growth. If selected as developer, we will coordinate a sewer capacity analysis with the sanitary district and identify any necessary improvements before final design.  Ultimately, the sanitary wastewater system for both sites will need to be reviewed and approved by the Sausalito-Marin City Sanitary District.
We are not proposing a major reconstruction of Coloma Street. The current concept includes frontage sidewalk improvements, but drainage, parking, access and pedestrian safety need to be worked through with the City and neighbors.

Construction

Construction will be required, at minimum, to follow the City’s permitted hours and approved construction controls. We will work directly with the schools on drop-off, pickup, dust, noise and truck routes. The exact monitoring and shutdown protocols should be established in the construction management plan, not improvised once work starts.  Initially, construction will occur Monday through Fridays between 8:00 a.m. and 6:00 p.m. per City of Sausailito Municipal Code Section 12.16.140. If Saturday work ever is to occur, those hours, per City Code would be 9:00 a.m. to 5:00 p.m.  Construction activity will comply with the City of Sausalito Municipal Code Section 12.16.  Dust control strategies that will be undertaken during construction was discussed extensively at the community meeting and may include standard safety measures such as daily watering down soil to prevent dust, perimeter air monitoring stations located around construction site to continuously monitor particulates (dust) where alarm notifications are automatically triggered if readings exceed specified limits. When alarms are triggered, construction activity must cease until readings recede to within specified limits. Minimizing disruption and inconvenience of the schools at Site 84 during operating hours and especially during drop-off/pick-up times will be determined in collaboration with the schools and the developer, which commits to creating a construction plan that works for all parties.  The construction plan would also include regular communication with neighbors, schools, and community including direct contacts info for the future construction company and developer.
We have no preconceived notions of how either site's construction activities will be staged.  We have not chosen a construction staging area or truck route. Those decisions should follow a detailed construction management plan reviewed by the City, schools and affected neighbors. We will not assume Coloma can absorb every construction need.  As stated during the community meeting, the The Richman Group development team will prepare the CMP based on input received during the community planning process.
The City has enforcement authority under its permits and applicable law; our superintendent also needs clear authority to stop an unsafe activity immediately. We support objective monitoring and a clear process for neighbors to report concerns. Specific thresholds and locations still need to be established.  Again, The Richman Group development team is committed to working closely with adjacent stakeholders at both sites to mitigate the impacts of noise, vibration, dust and other construction activities while maintaining compliance with applicable Muncipal building codes.
Our preference is to finance the sites together and build them on roughly the same schedule. That is the proposed plan, not a guarantee: permitting, funding and site conditions could change the sequence.

Environmental Impact

Yes, but to confirm: We expect to pay for appropriate independent site testing (soils & building materials within the existing buildings to-be demolished) and to address any contamination identified through that work.  That much is performed prior to any construction and can be shared.  During construction, if monitoring shows an unsafe condition attributable to construction, the affected activity will stop while it is evaluated and corrected. We need qualified professionals and regulators to set the actual testing and stop-work criteria.
We want to preserve mature oaks wherever practical. An arborist and survey will tell us which trees may be affected and what protection is feasible. We cannot promise that every tree will remain before that work is done.  
The point of performing an environmental site assessment is to avoid surprises and to determine early on in the predevelopment process what environmental issues, if any, need to be addressed as part of Sites 75 and 84's development.  Typically, we would incorporate the cost of envrionmental mitigation into the development budget.  If a costly environmental issue is discovered during due diligence, the developer may negotiate with the property owner (the City) how this clean-up issue is funded.
It is in an underground culvert, not open.
There are no plans to disrupt or work on the tennis courts, so the underground stream would not be impacted.
The City will need to determine the applicable CEQA pathway with its counsel and consultants. 
Performing and environmental site assessment for both sites will be one of the initial due diligence activities that will be undertaken if we are the selected developer.  This report will be publicly available and any contaminants or other hazardous conditions that may be revealed by the assessment will need to be mitigated in compliance with regulatory standards.
Yes, we are open to sharing air-quality monitoring results on a regular, understandable schedule. The frequency, locations, thresholds and reporting method should be agreed upon with the City and qualified consultants before construction.
Note we're simply in an RFP process to see if the City selects us as the developer - so we are unaware if the City has performed any kind of impact study.  If selected, we would first review the City’s existing studies, identify what remains unanswered, and complete any additional analysis required by the City and applicable law.
We do not know yet. If an archaeological study is required, such a study would reveal the potential existence of archaelogical remains. If archaeological resources are encountered, work would follow applicable discovery and protection protocols. Any needed cultural-resource assessment should be identified during preconstruction review.

Parking/Traffic

Our concept plan shows approximately one on-site parking space per apartment. That does not mean residents can own only one car.  If selected as the City's development partner, we would examine further likely demand.
Our intent is to keep the existing park parking available to park users, and restrict it from being residential spill over parking. We will work with the City on signage or enforcement if needed.
Construction workers need a parking plan too. We would identify designated parking and discourage parking that displaces neighbors or school users. The details belong in a City-reviewed construction management plan.  
We recognize that MLK Park parking serves families, sports teams and events—not just nearby residents. Our concept does provide slightly more public parking than what is there now.  We are open to working through a process to try and increase/maximize public parking within our plan.  
We have considered structured parking, but it is very costly for projects of this size and may conflict with the height and site constraints. We are not proposing it today. We should first establish actual parking demand and evaluate less costly options.
Drop-off and pick-up logistics for students at Lycée Français, New Village School and the Little Village Preschool during construction at Site 84 will be worked out in collaboration with the developer and schools.  Developer acknowledges that the schools are "protected uses' and every effort will be made to minimize any disruptions to the schools' existing operations.  Post occupancy of the the new housing at Site 84, we anticipate routing of school buses and family drop-offs/pick-ups to be similar to current conditions.
Traffic review requirements and thresholds are determined by the City under applicable rules. We would provide the project data needed to evaluate cumulative traffic conditions, including other reasonably foreseeable development.

Resident Community

Our current proposal is senior affordable housing (50 units) at Site 84 and family affordable housing (30 units) at Site 75. Site 84 is proposed as senior housing, with an on-site manager unit. The final eligibility and affordability structure will be set through the financing and regulatory process.
These are people and businesses with long-standing ties to the site, and their future deserves more than a quick answer. The City is the current landlord with primary responsibility.  To the extent we are included in the process, we offer to assist the City on a clear, lawful transition plan.
Housing works best when residents feel part of the town. We would welcome opportunities for shared activities, volunteer programs and partnerships with local schools and community organizations. Those ideas need to be shaped with residents and neighbors, not dictated from a conference room.  We offer social services to our residents which are another good opportunity for community engagement.  Lastly, we continue to own and manage our developments with heavy incentive to play a positive role within the community.
The City is the current landlord and must address existing leases and legal notice requirements. We would participate in a coordinated transition plan, but we cannot give a responsible notice date until those obligations and the project schedule are understood.
Fair housing laws limit restricting the planned new housing to Sausalito residents or special groups such as first responders.  However, as described at the Community Meeting, The Richman Group development team is committed to working with the community and the City to develop a plan for undertaking aggressive affirmative marketing and outreach to Sausalito residents, teachers and essential workers to maximize the opportunities for such workers to obtain housing in the new units. 

Financing

We are hoping to be selected as the City's development partner.  To-date we have simply submitted a concept with preliminary underwriting.  If we are selected, there is still much to negotiate.  We understand the concern about the City receiving value for its land. A shorter repayment period would change the project economics. We expecting to review the proposed underwriting and compare tradeoffs for affordability and feasibility.
There is no guarantee of an award, and we would not suggest otherwise. We have a strong track record and believe this proposal can compete, but public funding is limited. We are not assuming the City will automatically cover a shortfall. If funding falls short, we would bring the options and tradeoffs back to the City before changing affordability, design or City contributions.  Funding cannot be pursued by the development team until it is selected as developer and has a City-approved project that is ready for construction.  The Richman Group development team has regularly obtained financing for dozens of similar projects over the years and is confident that the developments at Site 84 and Site 75 will be highly competitive for State funding, County funding and private lenders and investors.  Our plan to consolidate both sites into a single project financing, we believe, increases the certainty of funding as this approach makes the development more cost effective and streamlined.  As with any project, if the projects fail to obtain financing after diligent pursuit, a rethinking of the development program, unit mix, etc. is always possible.
Yes, stormwater infrastructure is required and will be funded from the project's development budget. See responses to questions 32 and 71 for more detail.
Typically, the financial impact of wind and dust shutdowns, if any, are negligible and potential construction delays are absorbed into the construction schedule.  However, extended shutdowns for dust mitigation, rain or any other reason can lead to construction delays that lengthen the schedule.  Any such delays require the developer to pay the general contractor a daily rate for its general conditions/requirements at an agreed upon amount prior to start of construction.  Additionally, time equates to more interest payable on the construction loan and extensions to construction period insurance.
Yes, the senior apartments are also proposed as income-restricted affordable housing. Exact income tiers and rents will be confirmed through the final financing and regulatory agreements.
The Richman Group would be responsible for day-to-day operations, maintenance, reserves and long-term financial performance. We expect ongoing compliance reporting to the agencies that fund and regulate the property. Serenity in Larkspur has operated under an entirely different, and more aggressive, economic model.  Serenity is an apples to oranges comparison to our proposed financial structure.

Other

Yes. Like other professionally managed rental communities, these properties would have reasonable lease rules on noise, safety and consideration for neighbors, applied consistently with fair-housing requirements.
No project-based Section 8 assistance is currently assumed for Site 75 in our proposal. The apartments are intended to be income-restricted affordable rentals. 
These are income restricted rental apartments, so real estate sales agents are not part of the lease-up. Residents would apply through a publicly advertised, fair-housing-compliant leasing process managed by the property operator.
Good catch.  On our "General Assumptions" summary we include 1st Month at 100% Occupancy of 4/30/30.  But our monthly lease up schedule starts erroneously with Jul'27.  This should be Dec'29.  This is a formatting error does not impact the underwriting.  In fact, it appears to be a transcription error from when formatting our written RFP response.
The City would retain the underlying land under the proposed long-term ground lease. A project ownership partnership involving  The Richman Group, Pacific Housing and a tax-credit investor would own and operate the improvements subject to the lease and regulatory agreements. 
We expect standard initial one-year rental leases with renewals, subject to the applicable affordable-housing program and tenant protections. Income certification requirements will also apply.
We would establish a named community contact for the general contractor and for the developer, publish construction notices and provide a straightforward way to raise concerns. We should agree on response times and reporting frequency with the City (and the community) before construction begins.
We do not intend to use the MLK athletic facilities as construction storage. Any temporary use of public space would need separate City approval and a plan that protects park users.
The current concept shows roughly five feet along the north property line. That is preliminary and may change as surveying, code review, privacy screening and building design advance.
Under the proposed ground lease, the land remains City-owned. At expiration, the lease would govern whether the parties extend it or the improvements revert to the City.